Lake Mead critical elevation guide
Lake Mead Minimum Power Pool: 950 Feet Explained
Reclamation identifies elevation 950 feet above mean sea level as Lake Mead's estimated minimum power pool: the lower boundary for generating hydropower through Hoover Dam's turbines.
In brief
What this elevation does—and does not—mean
- Reclamation calls 950 feet the estimated minimum power pool and the top of inactive pool.
- Below this elevation, water cannot be passed through the turbines for generation, but releases can continue through the river outlet works.
- Minimum power pool is 55 feet above Hoover Dam's 895-foot dead pool.
What minimum power pool means
Minimum power pool is the lowest reservoir elevation at which a hydropower plant can produce electricity. For Hoover Dam, Reclamation currently uses an estimated elevation of 950 feet above mean sea level.
Generation capability declines before Lake Mead reaches that line as hydraulic head decreases and fewer turbines remain suitable for use. The threshold identifies the lower physical boundary; it is not a claim that output stays constant above it.
Why the threshold moved from 1,050 to 950 feet
Between 2011 and 2016, Reclamation installed five wide-head turbines at Hoover Dam. Its 2022 reservoir-capacity allocation says those units extended the estimated lower elevation for safe turbine generation from 1,050 feet to 950 feet.
That history is why older references may still associate 1,050 feet with minimum power pool. The current Reclamation allocation sheet and July 2026 Final EIS use 950 feet.
What happens between 950 and 895 feet
Below 950 feet, releases can no longer pass through the turbines for hydropower. Reclamation describes elevations from 950 down to 895 feet as inactive pool, where releases can continue through the river outlet works but face low-elevation constraints.
This distinction matters when reading forecasts: a projection below minimum power pool is a hydropower warning, but it is not yet a projection below dead pool.
Primary references
Sources
- Bureau of Reclamation: Lake Mead Reservoir Capacity Allocation (2022)
- Bureau of Reclamation: Post-2026 Final EIS, Technical Appendix 15 (July 2026)
Forecasts are planning information, not guaranteed outcomes. Use official Reclamation notices for current operating decisions.